How to use this tool
- Enter average daily demand, its standard deviation and selling days per year.
- Add the lead time (and its variation, if you know it) and your desired service level, for example 95%.
- Fill in the cost of one order, the unit price and the holding cost, as a percentage or in RON.
- Read the EOQ, reorder point and safety stock and compare with the quantity you order now.
How it is calculated and what to know
What EOQ is
EOQ (Economic Order Quantity) is the order quantity that minimises the sum of ordering cost and stock-holding cost. Small orders cost a lot to place, large ones cost a lot in storage and tied-up money. The formula is EOQ = √(2 × D × S ÷ H), where D is annual demand, S the cost of one order and H the holding cost of one unit per year (price × holding percentage).
Safety stock and reorder point
Safety stock protects against variation in demand and lead time: SS = z × √(lead time × σ² + demand² × σ_lead²), with z the normal-distribution value for the service level (1.28 at 90%, 1.645 at 95%, 1.96 at 97.5%, 2.33 at 99%). The reorder point is daily demand × lead time + safety stock: when stock falls to it, you place the order.
Worked example
Demand 20 pcs/day (deviation 6), 365 days, so D = 7,300 pcs a year; order cost 120 RON; price 50 RON; holding 20% (H = 10 RON/pc/year); lead time 7 days; service 95%. EOQ = √(2 × 7,300 × 120 ÷ 10) ≈ 419 pcs, i.e. 17.4 orders a year, about every 21 days. Annual ordering and holding cost is 4,186 RON. Safety stock = 1.645 × 6 × √7 ≈ 26 pcs; reorder point ≈ 140 + 26 = 166 pcs. If you ordered 1,000 pieces at a time, cost would be 5,876 RON, 40% more.
Limits
The classic model assumes steady demand, no quantity discounts and delivery in a single batch. If your supplier offers volume discounts or you stock perishables, the result is only a starting point. The cost of the goods does not depend on quantity and is not in the chart.
Frequently asked questions
How do I calculate the economic order quantity (EOQ)?
Use the formula √(2 × annual demand × cost per order ÷ holding cost per unit per year). With 7,300 pcs a year, 120 RON per order and 10 RON holding, the result is about 419 pcs.
What does reorder point mean?
It is the stock level at which you place the order so the goods arrive before you run out: demand during the lead time plus safety stock. In the example on this page it is 166 pcs.
What service level should I choose?
For most products 95% is a good compromise. For critical or high-profit items choose 97.5–99%; each step up needs more safety stock, so more tied-up money.
How do I find the standard deviation of demand?
Take daily sales from the past weeks or months and apply STDEV in Excel or Google Sheets. The more erratic sales are, the larger the safety stock.
What is stock-holding cost?
It is the cost of keeping one unit in stock for a year: interest on tied-up money, storage space, insurance, losses and obsolescence. It is usually estimated at 15–30% of the unit price per year.
Module created by Succes Grup.
Other useful tools
Cash conversion cycle (CCC) and working capital calculator
Find how many days the money in stock takes to return and how much working capital you need.
Open Markup and marginMarkup and margin calculator (with VAT) 2026
From cost, markup or margin find the price incl. VAT, the profit and the effect of a discount.
Open Online profitMarketplace and online shop profit calculator (with returns)
Find your net profit per unit and per month and the price you need for your target margin.
Open